Sixwaysrugby Forum  
Week 1 Week 2 Week 3 Week 4 Internals Week 6 Week 7 Week 8 Week 9 Week 10 Changes 1  
Changes 2 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20  

From This - May 2008 To This - September 2008
         

A Bit of water still around but a lot of work going on up at Sixways.

The foundations have now been prepared for the East Stand Build work

               

Concrete has been poured and the steel bolts inserted to hold the supports for the Extension and Cantilever Roof

               
Line of Foundation Holes at the rear of East Stand Looking East from the North Stand
Looking North from the back of the old club shop.

Looking into the area where the supporters will meet and partake of the atmosphere. It is a huge area

               

Looking West from the side of the East Stand

All the tarmac has been removed and the hard core laid down where the brook used to be and the North Stand entrance turnstile

               

The filling in of the Old Brook

On top of this will be the new office and reception area.

The brook has been diverted away from this area.

               

The pitch has been sanded and levelled, in preparation for the start of next season.

Each year our pitch gets better, I should imagine next year it will start to approach the surface at Northampton

               

Wouldn't it be fantastic if they turned this are into a standing terrace just as at Saints and Tigers.

There will be another 4 rows above the existing rows.

Better still "NO SUPPORTS" obstructing your view as we install a state of the art cantilever roof

               

This is the new route of the brook as it runs next to the road and goes into the new ducting.

This will take it around the new North stand and into the waterfowl protected pool at the back of the complex